Completion Procedures
Completion and Equipment Procedure
- Move in work over rig
- Run a cased hole bond log, gamma ray log, and collar locator
- Run in the well bore with a perforating gun and perforate the well at the area of production
- At this time stimulate the well if needed. Some wells need multiple stages of stimulation.
- Run in the well bore with production tubing and set packer above producing zone
- Flow well back
- Test well for oil and gas production quality and quantity
- Set-up storage tanks and stairwell, heater treater, tank battery, separator, water tanks, flow lines, meter loop, gas lines
- Contract with gatherers for sale of oil and gas.